Costs

Overview

The Costs screen adds up what your finished work cost over a period – labor, drive time, materials, expenses and mileage – and sets it beside what that work earned. Owners and managers find it under Money in the web sidebar, and under More in the mobile app.

The Costs page with Spent, Earned and Left over totals and the day-by-day table

Plan availability: Costs is on the Business plans (and Enterprise). See Billing & Plans.

At the top are three figures for the period: Spent, Earned and Left over, with the number of completed jobs behind them. Nothing here needs approving; receipts are reviewed in Expenses.

What the Page Tells You

Above the figures, What this page tells you sums up the period in a few sentences: what finished jobs cost and earned and what was left over, which cost was the biggest and how much of the earnings it took, how much paid crew time did not land on a finished job, and what was spent away from jobs.

Every figure has a ?: point at it, or tap it on a phone, for a short explanation and a link to the part of this article that covers it. The three totals at the top are rounded to the whole dollar (or your currency’s whole unit) so they read at a glance; the tables below keep the cents.

Choosing a period

Pick a Period – Last 30 days, This month, Last month, This quarter, Year to date, or Custom dates. The page opens on the last 30 days, the same as Profitability. There is no all-time option.

Day by day

One row for each day work finished on, with jobs, each cost, Spent, Earned and Left over. A crew’s return to base is counted on the day it was driven, even when no job finished that day. Periods longer than 45 days are grouped by week, and longer than a year by month.

Where it went

The spend is split into up to five buckets, largest first:

  • Labor – crew time on site (pauses excluded), at each member’s hourly rate.
  • Drive – the same rates applied to the time between on-my-way and starting the job.
  • Materials – the cost of the job’s line items.
  • Expenses – expenses logged against the job.
  • Mileage – the legs driven to the jobs, plus each crew’s Return to base in the period (see Mileage).

On the web, beside each amount is its share of sales: what it took out of what the work earned. The phone shows its share of the spend as well. A bucket with nothing spent in it is left out.

Labor: crew time against attributed

  • Crew time cost – every attendance shift in the period, at each person’s labor rate (their full hourly cost, see Team Management). It is the same arithmetic Timesheets uses.
  • Landed on jobs – the labor and drive time that finished jobs absorbed.
  • Not attributed to a job – the difference.

A job only absorbs the time between its start and its finish, so breaks, travel between stops, loading up before the first visit, and work on jobs that have not finished yet all land in that last number. While somebody is still clocked in, the page notes that the labor figure is still moving.

By crew member breaks the same figures down per person, with hours and rate. On the web, Open timesheet goes to that person’s timesheet.

Spend away from jobs

Expenses that are not attached to a job – fuel, office supplies, a team lunch – are listed separately, grouped by category. They are not included in Spent above, and job expenses are not repeated here.

What the totals cannot see

Only finished work carries a cost. A job is costed when it is completed, so jobs still scheduled or in progress contribute nothing. The period covers what finished in it, not what was worked on.

Missing inputs make the total a floor. A team member with no labor rate costs nothing in these figures, and a catalog line with no cost leaves materials short. A warning at the top counts them, and also counts visits whose headcount had to be estimated. On the web, Set labor rates takes you to Employees, where each member’s Labor rate is set – or, when the only missing rate is the owner’s own, to My company > Profile (see Team Management).

What You Can Do

Beside the summary, What you can do lists up to three suggestions picked from the period’s numbers, most urgent first, each with a link where there is something to open:

  • People in the field with no labor rate – Set rates.
  • Finished work that cost more than it earned – Open Profitability to find the stops that lose money.
  • More than a quarter of paid crew time not landing on a finished job – Open timesheets.
  • Labor taking more than half of what the work earned, or materials more than 40% – Open Profitability or Open catalog.
  • Driving taking more than 15% of what the work earned, or visits where nobody clocked in.

These thresholds are rough rules of thumb for field service, not targets. The suggestions are worked out from your numbers by fixed rules; they are a starting point, not advice tailored by a person.

Costs and Profitability

Costs shows what the whole company spent in a period; Profitability shows which individual stops are worth doing. Both read the same job costs, so they agree on what a job cost. The one difference is a crew’s return to base: it belongs to no job, so it is counted here and on no stop. See which stops lose money on the Costs screen opens it.