Profitability

What It Answers

The Profitability page shows, for every stop, how long it takes against its plan and what an hour of crew time earns there. It is part of the Business plans. Owners and managers open it from the Team section of the menu.

Each row shows:

  • On site / visit – Average time on site, against the job’s Estimated duration. Red when visits run past the plan.
  • Per hour – Earned minus materials, expenses and mileage, per hour of crew time, the drive included. A dash means no crew time was recorded, and the time column says No time logged.
  • Earned / visit – The job’s line items, price times quantity.
  • Margin / visit – Earned minus labor, drive, materials and expenses. Red when the stop loses money.

What the Page Tells You

The top of the page says in plain words what the period comes down to: how many visits were finished and what they earned, how many stops lost money, earned under your minimum or ran long, and what an hour of crew time brought in overall.

Below it, the stops are sorted into groups, each with a heading that says what its stops have in common:

  • Losing money – the stop costs more than it brings in.
  • Earning under your minimum – it covers its costs, but an hour of crew time brings in less than your minimum per hour.
  • Taking longer than planned – it makes money, but visits run past the estimated duration.
  • Doing well – it covers its costs, earns at least your minimum and finishes on time.
  • Can’t tell yet – no crew time was logged, so time on site and earned per hour can’t be worked out.

Each stop goes into one group only, the worst that applies: a stop that loses money and also runs long is under Losing money. Within a group, the stop earning least per hour comes first.

Every figure and badge on the page has a ? or explains itself: point at it, or tap it on a phone, for a short explanation and a link to the part of this article that covers it.

Large figures are rounded to the whole dollar (or your currency’s whole unit) so they read at a glance; the receipts on a stop’s page keep the cents.

Why Time Comes First

Margin depends on who was on the truck. A $60 lawn planned for one hour leaves $25 when a hand with a $35 labor rate mows it in the hour, and $30 when a newer hire at $15 takes two. A labor rate is the whole cost of an hour of that person: wage, payroll taxes, insurance and benefits. The slow visit looks better on margin, yet it took double the plan and earned $30 an hour, not $60. Time on site and earned per hour do not change with labor rates, so they lead the page.

Where the Numbers Come From

Nothing is typed in. Every figure comes from what your crews already do:

  • Labor – From Start job to Finish job, minus any time the job was paused, at the Labor rate of each crew member who clocked in that day. Set rates on the Employees page – a warning above the list counts who has none, and Set rates takes you there; the owner’s own rate is Your labor rate on My company > Profile (see Team Management).
  • Drive – From On my way to Start job, at the same rates, plus the job’s mileage entries. A crew’s return to base at the end of the day is not on any stop; it is counted on Costs. With Crews start and end the day set to From home, the drive to the first job has no entry either.
  • Materials – The cost on each line item, times quantity.
  • Expenses – Every expense logged against the job, billed or not.
  • Crew time – On-site plus drive time, times the number of people on the visit.

The numbers are captured when a job is finished. An expense or mileage entry added later updates that visit on its own; new labor rates or catalog costs need Recalculate.

Reading the List

Each row is one stop. A recurring job is one row with its visits in the period averaged; a one-off job is its own row.

The Profitability page with the earned-per-hour tiles and a stop flagged under target

The rows are grouped as described in What the Page Tells You, worst group first.

The tiles above the list give the period’s visits, earned, earned per hour, stops under your minimum (when one is set), and stops over plan. Cost, margin and the number of stops losing money sit on the line underneath. Earned per hour counts only the visits that logged crew time; when some did not, the tile says how many it is based on, such as Based on 9 of 12 visits with time logged.

What the Badges Mean

Badges on a row, a stop’s page or a visit:

  • Under target – Earned per hour is below your minimum. The stop may still make money, but it pays less than you want for the time.
  • min over plan – On average, visits ran this many minutes past the estimated duration.
  • Missing inputs – A crew member on the visit has no labor rate, or a priced part has no cost. The cost shown is lower than reality; fill them in and press Recalculate.
  • Headcount estimated – Nobody on the crew clocked in that day, so the whole crew was assumed.
  • No time logged – The crew never tapped Start job and Finish job, so there is no time on site or earned per hour.
  • No estimate – The job has no estimated duration to compare with. Add one on the job and the comparison appears.
  • no labor rate set – On a visit’s receipt, this person has no labor rate, so their time costs nothing.

What You Can Do

Beside the summary, What you can do lists up to three suggestions picked from the period’s numbers, most urgent first, each with a link to act on it:

  • People in the field with no labor rate – Set rates.
  • The stop that loses the most per visit, the stop earning least under your minimum (with roughly how much more each visit would need to reach it), or the stop that runs longest over its plan – Open stop.
  • Stops costed before a rate or a part cost was filled in – Open catalog, then Recalculate.
  • Stops with no crew time, days nobody clocked in, jobs with no estimated duration, or no minimum set.

A stop’s own page lists its suggestions under its verdict, such as how much to raise the price to break even, with Open job to change it. The suggestions are worked out from your numbers by fixed rules; they are a starting point, not advice tailored by a person.

Picking a Period

The Period picker offers Last 30 days (the default), This month, Last month, This quarter, Year to date, and Custom dates, which takes a From and To up to two years apart. The Crew filter narrows the list to one crew’s stops.

Setting a Minimum Per Hour

Every company starts with a minimum of $50 an hour. Change it in the field under the filters and press Save; the rows update at once. It is also Minimum earned per hour on My company > Money & payments, where the Pro plans set it too: the estimate on a quote checks each price against it. In the mobile app, Change beside Your minimum per hour in a quote’s Estimate section sets it as well.

The minimum has to cover labor, overhead (trucks, insurance, rent, office, software) and profit. A rule of thumb: divide a year of overhead by the hours your crews work in a year, then add your average labor rate and the profit you want per hour.

A stop earning less than the minimum turns red and gets the Under target badge, even if it didn’t lose money. Press Clear and only stops that run over their plan or lose money are flagged.

Opening a Stop

Click the stop’s name or Details. The top shows time on site against the plan and earned per hour, then the period’s totals with the per-visit average under each, and a chart of where the cost went: labor, drive, materials, expenses.

Below, every visit is laid out like a receipt: what it earned line by line, and what it cost – each crew member with their minutes on site, minutes driving and hourly rate, each mileage entry, every part with its unit cost, and every expense.

Click a visit’s date to open that day’s job. Open job opens the recurring job itself, where you change the price.

Recalculating

After entering labor rates or catalog costs, click Recalculate to redo every visit in the period. A progress bar counts the visits, and the page reloads on its own when the last one finishes. A visit it could not redo keeps its old numbers and is counted in a warning; run it again.

From the Mobile App

Owners and managers get the same page in the mobile app under More, with the same periods, crew filter, minimum, Recalculate, and per-visit detail. See Mobile Management App.